Carpeting Started On Padma Bridge

Staff Reporter: Carpeting of road (bituminous work) has started on Padma bridge. The work started at 9.40 am on Wednesday (November 10). Road Transport and Bridges Minister, Obaidul Quader is overseeing it.

According to the Ministry of Road Transport and Bridges, another feather has been added to the crown of the Padma Bridge.

The carpeting work is being done by the contractor China Major Bridge Engineering Company (MBEC).

It is learned that the construction work of the main bridge has been completed 95 percent in the meantime. About 69 percent of the projects have made overall progress. And the progress of river governance work has been 7 percent. The work of connecting the road between Mawa and Jajira has been completed.

Those concerned hope that the Padma Bridge will be fully operational before June next year. Then crossing will be a dream, crossing will be immense possibilities. The movement will be fast. Growth will increase.

Copyright © Sunnews24x7
Most
Readed
Recent

Four brothers died from toxic gas: Oman police

Police in Oman have launched an investigation in...

Four brothers died from toxic gas: Oman police

Police in Oman have launched an investigation in...

Measles and symptoms deaths pass 450

Another 12 children died in the country in the l...

SSC and HSC 2027 exam dates announced

The Secondary School Certificate (SSC) and equival...

Trump expecting Chinese support for Iran deal

US President Donald Trump is seeking China’s support for a possible dip...

Padma Barrage: Tk 344.97b project approved

The government has undertaken the ‘Padma Barrage (1st Phase)’ pro...

sunnews27x7 advertisement
Lifestyle
Entertainment
sunnews24x7 advertisement
Sports